Required Documents |
- Service Request Form
- Building Permit
- Copy of Personal ID
- Clearance Certificate
- No Objection Certificate
|
Processing Time |
1200 minutes (4 days) |
Fees |
- Main: 1000 + 32 shekels per amp (above 32 amps)
- Secondary: 700 + 32 shekels per amp (above 32 amps)
|
Legal Basis |
- Buildings Regulation 2011 and its amendments
- Municipality rules and procedures
- Municipal council decisions
|
Execution Procedure |
- Receive request at Public Service Center
- Forward to Engineering Department to check permit file
- Field inspection for installation feasibility and cost estimate
- Forward to Accounting to calculate fees and installation charges
- Notify citizen of the result via Public Service Center
- Forward to Electricity Department for installation
- Send file to Accounting to record subscriber data in the financial system
|
Implementing Department |
Electricity Department |