Azzun
Electrical Department Services<>خدمات قسم الكهرباء<>

Single-Phase Electricity Subscription Request

4.01 Single-Phase Electricity Subscription Request





























Required Documents

  • Service Request Form

  • Building Permit

  • Copy of Personal ID

  • Clearance Certificate

  • No Objection Certificate


Processing Time 1200 minutes (4 days)
Fees

  • Main: 1000 + 32 shekels per amp (above 32 amps)

  • Secondary: 700 + 32 shekels per amp (above 32 amps)


Legal Basis

  • Buildings Regulation 2011 and its amendments

  • Municipality rules and procedures

  • Municipal council decisions


Execution Procedure

  • Receive request at Public Service Center

  • Forward to Engineering Department to check permit file

  • Field inspection for installation feasibility and cost estimate

  • Forward to Accounting to calculate fees and installation charges

  • Notify citizen of the result via Public Service Center

  • Forward to Electricity Department for installation

  • Send file to Accounting to record subscriber data in the financial system


Implementing Department Electricity Department

Work Flow














Public Service Center Engineering Department Electricity Department Accounting Department Public Service Center Electricity Department Accounting Department