- Service Request Application Form
- Building Permit
- Copy of Personal Identification
- Clearance Certificate
- No-Objection Certificate
|
Required Documents |
|
|
Required Completion Time |
- 1000 Main + 32 NIS per ampere (Above 32 Amps)
- 700 Sub + 32 NIS per ampere (Above 32 Amps)
|
Required Fees |
- Building Regulation of 2011 and its amendments
- Municipal regulations and procedures
- Municipal Council Decisions
|
Legal Reference |
- Application received by the Public Services Center
- Transferred to the Engineering Department to review the licensing file
- Field inspection to assess installation feasibility and estimate costs
- Transferred to Accounting Department to calculate dues and pay installation fees
- Applicant notified of the result through the Services Center
- Transferred to the Electricity Department for installation
- File transferred to Accounting for archiving and adding subscriber data to the financial system
|
Implementation Procedure |
|
|
Implementing Authority |